Risk management in renewables
.jpg)
As renewable energy projects mature in scale and complexity, risk management has become a critical differentiator. Beyond technology selection and financing, businesses must ensure that their solar and battery assets perform over their 20-year life cycles.
This white paper explores the key risk factors facing renewable projects in Australia, the role of insurance and warranties, and practical steps businesses can take to safeguard long-term performance and returns.
The Evolving Risk Landscape in Renewables
• Performance risk: Will the system deliver the forecasted kWh over 10-20 years?
• Technology risk: Rapid innovation increases the risk of premature obsolescence.
• Grid risk: Export curtailment, dynamic operating envelopes, and evolving DNSP rules.
• Grid risk: Export curtailment, dynamic operating Climate risk: Harsher weather events-floods, hail, bushfires- threaten assets more than ever.
• Counterparty risk: EPCs, O&M providers, and even equipment manufacturers may not be around in 10 years.
Why it matters: Energy assets are only valuable if they generate and store power consistently. A single underperforming year can erode IRR and delay payback by several years.
Insurance in the Renewable Sector
Insurance isn't just a box to tick - it's your safety net.
• During build - Covers damage in delivery or installation delays.
• Once operational - Protects against storms, fires, floods, and lost generation revenue.
• New risks - Cyber cover for monitoring platforms and environmental liability for batteries are now common.
Agile Tip: Always check the fine print - many policies exclude common issues like "design defects" or cap payouts for weather damage.
Warranties: Know the Limits
Warranties sound reassuring, but they're not all equal.
• Panels - Usually 25 years for performance, but terms vary (linear vs. stepped coverage).
• Inverters - Often 5-10 years; these are the most common failure point.
• Batteries - Coverage based on cycles or years; must match your
usage.
• Workmanship - Covers how your system was installed.
Reality check: A warranty is only as strong as the company behind it. If the manufacturer disappears, the promise disappears too.
Keeping Systems at Peak Performance
The best defence is active management:
• Independent engineering checks before construction.
• Performance guarantees written into contracts.
• Real-time monitoring to catch issues early.
• Regular cleaning, inspections, and updates.
• Partnering with a specialist to manage the asset long term.
How Agile Energy Protects Clients
At Agile Energy, risk management is built in from the start:
• Before build - Structural checks, grid connection due diligence, and only bankable technology.
• During build - Full insurance cover, warranties transferred directly to the client.
• In operation - 24/7 monitoring, routine maintenance, and two years of defect liability included.
• Beyond - Optional extended O&M packages, including cleaning and asset optimisation.
Solar and battery projects should be safe, predictable investments. But without the right insurance, warranties, and performance management, returns can quickly erode. By protecting your assets properly, renewables become what they should be: a reliable, long-term source of savings and resilience.

Managing solar and battery rollouts for national portfolio

Commercial Solar ROI in 2025: Maximise Your Business Savings

Scaling SAFe in large-scale energy organisations: How executives can harness the Scaled Agile Framework (SAFe) to accelerate the energy transition

Always-On Agile operating model for Australia’s energy transition

Integrated energy & carbon strategies: A Playbook for future-proofing Australian manufacturing

Weathering the storm: Protects solar assets from heavy rainfall risk

Transforming dead space into active assets: How Agile unlocks roofs, car parks, and land for revenue

Agile Advantage - Why energy data is the new gold for Australian manufacturer

Solar Battery Rebate

Agile Advantage - E is Everything: Energising Australian Businesses

Agile Advantage - Riding the renewable wave: Why Australian businesses are embracing solar energy

Agile Advantage - Why CFOs should prioritise renewable energy investments in 2025

Agile Advantage - Empowering Australian Businesses: Unlocking energy efficiency and sustainability

Agile Advantage - Inspiring the young workforce: How rolling out renewables sparks motivation

Agile Advantage- The power of vertical integration in solar project delivery

Agile Advantage - Making complex simple: Navigating the complexity of solar installations

Agile Advantage - Rising cost of insurance : Impact on solar assets

Agile Advantage - Monetising your solar assets: Converting pre-purchased systems into power purchase agreements (PPAs)

Agile Advantage - The Magic of experience: Partnering for performance in renewables

Agile Advantage - Solar rooftop safety: Risk management guide

Agile Advantage - Clear paths to carbon reduction: Renewables and more for Australian businesses

Agile Advantage - Seven Deadly Sins of Solar Installations: Mistakes Businesses Must Avoid

CEO's view on managing increasing energy costs

Carbon Accounting and your business

Join Agile Energy at the Healthcare Real Estate Summit

Carbon Projects - Where to Start?

TRADE ACCUs WITH US! From the desk of Equipoised Group
Ready to Power Your Business with Sustainable Energy?
Let's take the first step towards a brighter and greener future.